Tuesday, June 24, 2014

Humans suck at statistics - how agile velocity leads managers astray

Humans are highly optimized for quick decision making. The so-called System 1 that Kahneman refers to in his book "Thinking fast, thinking slow". One specific area of weakness for the average human is understanding statistics. A very simple exercise to review this is the coin-toss simulation.

Humans are highly optimized for quick decision making.

Get two people to run this experiment (or one computer and one person if you are low on humans :). One person throws a coin in the air and notes down the results. For each "heads" the person adds one to the total; for each "tails" the person subtracts one from the total. Then she graphs the total as it evolves with each throw.

The second person simulates the coin-toss by writing down "heads" or "tails" and adding/subtracting to the totals. Leave the room while the two players run their exercise and then come back after they have completed 100 throws.

Look at the graph that each person produced, can you detect which one was created by the real coin, which was "imagined"? Test your knowledge by looking at the graph below (don't peak at the solution at the end of the post). Which of these lines was generated by a human, and which by a pseudo-random process (computer simulation)?

One common characteristic in this exercise is that the real random walk, which was produced by actually throwing a coin in the air, is often more repetitive than the one simulated by the player. For example, the coin may generate a sequence of several consecutive heads or tails throws. No human (except you, after reading this) would do that because it would not "feel" random. We, humans, are bad at creating randomness and understanding the consequences of randomness. This is because we are trained to see meaning and a theory behind everything.

Take the velocity of the team. Did it go up in the latest sprint? Surely they are getting better! Or, it's the new person that joined the team, they are already having an effect! In the worst case, if the velocity goes down in one sprint, we are running around like crazy trying to solve a "problem" that prevented the team from delivering more.

The fact is that a team's velocity is affected by many variables, and its variation is not predictable. However, and this is the most important, velocity will reliably vary over time. Or, in other words, it is predictable that the velocity will vary up and down with time.

The velocity of a team will vary over time, but around a set of values that are the actual "throughput capability" of that team or project. For us as managers it is more important to understand what that throughput capability is, rather than to guess frantically at what might have caused a "dip" or a "peak" in the project's delivery rate.

The velocity of a team will vary over time, but around a set of values that are the actual "throughput capability" of that team or project.

When you look at a graph of a team's velocity don't ask "what made the velocity dip/peak?", ask rather: "based on this data, what is the capability of the team?". This second question will help you understand what your team is capable of delivering over a long period of time and will help you manage the scope and release date for your project.

The important question for your project is not, "how can we improve velocity?" The important question is: "is the velocity of the team reliable?"

Picture credit: John Hammink, follow him on twitter

Solution to the question above: The black line is the one generated by a pseudo-random simulation in a computer. The human generated line is more "regular", because humans expect that random processes "average out". Indeed that's the theory. But not the the reality. Humans are notoriously bad at distinguishing real randomness from what we believe is random, but isn't.

As you know I've been writing about #NoEstimates regularly on this blog. But I also send more information about #NoEstimates and how I use it in practice to my list. If you want to know more about how I use #NoEstimates, sign up to my #NoEstimates list. As a bonus you will get my #NoEstimates whitepaper, where I review the background and reasons for using #NoEstimates

Subscribe to our mailing list

* indicates required

Labels: , , , , , , , ,

at 06:00 | 3 comments
RSS link

Bookmark and Share

Friday, April 30, 2010

Tired of useless boring planning meetings? Read on, I've got a solution for you


In a meeting today I was graphically reminded of how some of the basic concepts in software development still escape many of us. Case in point, the meaning of capacity.

In many people's minds capacity still means "how many man-hours we have have available for real work". This is plain wrong.

Let's decompose this assumption to see how wrong it is.


  1.  First, in this assumption is implicit that we can estimate exactly how many man-hours we have available for "real work". The theory goes like this: I have 3 people, the sprint is 2 weeks/10 days, so the effort available, and therefore capacity, is 30 man-days. This is plain wrong!!! How? let's see:

    1.  Not all three people will be doing the same work. So, even if you have a theoretical maximum of 30 man-days available not all people can do the same work. If, for example, 1 person would be an analyst, another a programmer and finally the third a tester, then that would leave us with effectively 10 man-days of programming, analysis and testing effort available. Quite different from 30 man-days!
    2. Then there's the issue that not 100% of the time available for each people can actually be used for work. For example, there are meetings about next sprint's content, then there's interruptions, time to go to the toilet... You get the picture. In fact it is impossible to predict how many each person will use for "real" work.

  2. Then there are those pesky things we call "dependencies". Sometimes someone in the team is idle because they depend on someone else (in or out of the team) and can't complete their feature. This leads to unpredictable delays, and therefore ineffective use of the effort available for a Sprint.
  3.  Finally (although other reasons can be found) there's the implicit assumption that even if we could know perfectly the amount of effort available we can know how much some piece work actually takes from beginning to end, in exact terms! This is implicit in how we use the effort numbers by then scheduling features against that available effort. The fact is that we (humans) are very bad at estimating something we have not done before, which is the case in software most of the time.
The main message here is: effort available (e.g. man-hours) is not the same as capacity. Capacity is the metric that tells us how many features a team or a group of teams can deliver in a Sprint, not the available effort!

Implications of this definition of capacity

There are some important implications of the above statement. If we recognize that capacity is closer to the traditional definition of Throughput then we understand that what we need to estimate is not just size of a task, plus effort available. No, it's much more complex than that! We need to estimate the impact of dependencies, errors, meetings, etc. on the utilization of the effort available.

Let me illustrate how complex this problem is. If you want to empty a tank of 10 liters attached to a pipe, you will probably want to know how much water can flow through the pipe in 1 minute (or some similar length of time) and then calculate how long it takes to completely empty the tank. Example: if 1 liter flows through the pipe in 1 minute then it will take 10 minutes to empty a 10 liter tank. Easy, no?

Well, what if you now try to guess the time to empty the same tank but instead of being given the metric that 1 liter of water can flow in the piper for each minute, you are instead given:

  • Diameter of the pipe
  • Material that the pipe is built in
  • Viscosity of the liquid in the tank
  •  Probability of obstacles existing in the pipe that could impede the flow of the liquid
  • Turbulence equations that allow you to calculate flow when in the presence of an obstacle

Get the point? In software we are in the second situation! We are expected to calculate capacity (which is actually throughput) given a huge list of variables! How silly is that?!

For a better planning and estimating framework

The fact is that the solution for the capacity (and therefore planning) problem in software is much, much easier!

Here's a blow by blow description:

  • Collect a list of features for your product (not all, just the ones you really want to work on)
  • With the whole team, assess the features to make sure that neither of them is "huge" (i.e. the team is clueless about what it is or how to implement it). If they are too large, split them in half (literally). Try to get all features to fit into a sprint (without spending a huge effort in this step). 
  • Spend about 3 sprints working on that backlog (it pays off to have shorter sprint!)
  • After 3 sprints look at your velocity (number of features completed in each sprint) and calculate an average
  • Use the average velocity to tell the Product Owner how long it will take to develop the product they want based on the number of Features available in the backlog
  • Update the average expected velocity after each sprint
Does it sound simple? It is. But most importantly, I have done many experiments based on this simple idea, and I'm yet to find a project where this would not apply. Small or big, it worked for all projects where I've been involved in the past.

The theory behind

There's a couple of principles behind this strategy. First, it's clear that if you don't change the team, the technology or any other relevant environmental variable the team will perform at a similar level (with occasional spikes or dips) all the time. Therefore you can use historical velocity information to calculate a long term velocity in the future! 
Second, you still have to estimate, but you do that at the level of one Sprint. The reason is that even if we have the average velocity, an average does not apply to a single sprint but rather to a set of sprints. Therefore you still need to plan your sprint, to identify possible bottlenecks, coordinate work with other people, etc.

The benefits

Finally the benefits. The most important benefit here is that you don't depend on estimations based on unknown assumptions to make your long term plans. You can rely on data. Sure, sometimes the data will be wrong, but compare with the alternative: when was the last time you saw a plan hold up? Data is your friend!
Another benefit is that you don't need to twist anyone's arm to produce the metrics needed (velocity and number of features in backlog), because those metrics are calculated automatically by the simple act of using Scrum.

All in all not a bad proposition and much simpler than working with unavoidably incorrect estimates that leave everybody screaming to be saved by the bell at the end of the planning meeting!