Wednesday, December 18, 2013

The most valuable question for your software project


Every time a software project is started, a dance starts: the dance of project approval. Decision makers and project delivery team take different positions at a table, some ask questions, others do their best to respond, given that these questions are typically about the future. Some of the questions are so much into the future that it would be foolish to pretend we know the answer. Yet we do.

This was the main lesson I learned in my life as a project manager: you have to learn how to dance.

How to dance...

In the dance-like meetings there are 3 types of people:

  • A) Those that pretend to know the future
  • B) Those that know they can't know the future
  • C) And those that don't want to know the future
The question below is only valid for the people in category B). The other two categories are beyond help from me or anyone else.

What is the likelihood this project will fail?

When a project starts, the best question anyone can ask about the project is this:
The most important question: What is the likelihood this project will fail? Why is this question important?

  • First, if you don't have an answer to this question you are either in the first or third category of those listed above, and there's nothing I (or anyone else) can do to help you.
  • Second, by discussing the possibility of failure we are actively looking for possible causes of problems for the project (rule 1 of risk management).
  • Third, having an actual conversation about the failure probability of a project will give you an indication of the "value at risk" for the project.

For example: let's say the project budget is about 100K dollar, and to make it a worthwhile investment we would need to make it between 120K and 90K in total cost (i.e. if it is likely it will cost more than 120K you should not do it). If the answer to the most important question is: 50/50, then you know that the project is not worth doing. It has very little chance of delivering the necessary value to justify it's existence, in fact: it is likely it will be above 100K and up to as much as 200K in cost.
However, if the answer is that we are 80% confident we will deliver the project on timecost, then the project is worth pursuing (although with some strict scope control in place) because the expected worst case scenario would be a total cost of 120K dollars (the 20% margin implicit in the confidence above). In practice an 80% confidence means you expect the project to cost up to 120K (100K + 20%) in the *worst* case.

In a later post I'll explain how we can answer this most important question using the #NoEstimates approach. For now, let me know what you think of the question and the concept of "value at risk" above.

Definition of Value-at-risk [PDF]: "value-at-risk summarizes the expected maximum loss (or worst loss) over a target horizon within a given confidence interval"

Note: A special thanks to @galleman for the idea of the 3 categories of people from which I derived the 3 categories I present in this post.

Photo credit: Steven Depolo @ flick

Labels: , , , , , , , ,

at 07:30 | 2 comments
RSS link

Bookmark and Share

Monday, December 02, 2013

Use #NoEstimates to create options and deliver value reliably

Why do I use #NoEstimates? Certainly the first reason is obvious in the name of this movement. But there are may other reasons. One of the reasons that does not get enough airtime is that it creates more options than using pre-estimated methods to manage software projects.
Value is unpredictable, generate options to explore the value space

When we estimate a software project we make certain assumptions about what work and how that work will be completed. We need to do that in order to sequence the work, handle the dependencies, assign the work to the right people, etc. Estimation is a process of planning, and as such it requires us to make commitments. Those commitments reduce our options, because we immediately eliminate possible implementation strategies.

Let's look at an example. I want to implement a IT-request queue in my organization. Something that allows us to manage the requests from employees in a way that none is lost and the employee can easily get information on how the item is proceeding through it's life-cycle. A project is started. How to plan this project?

  • The Estimated approach: In this approach I get the team together we list all the work that needs to be completed (database changes, UI for form input, queries and IT ticket management, server deployment, testing, etc.). We schedule this work according to skills and availability of people and end up with a schedule. This schedule will be implemented by different people. Because of this, I will have to follow-up with each person, to make sure we have each necessary task completed before the work on the next tasks begins. This is how we would typically handle the dependencies between these tasks.
  • The #NoEstimates approach: In this approach I ask the team: "What is the most important work that we need to complete NOW?". Tracy says: "The IT ticket handling is the most important part. We can add the customer-side UI later and handle incoming requests by email until then". Bingo! I get the list of tasks for that specific functionality from the team, and it looks much smaller: Database changes + IT UI development. The immediate benefit is that the dependencies are fewer (and we will make them even fewer with User Story splitting), which means less coordination, and valuable functionality delivered earlier. But the key point is this: We have more options! We have made the necessary commitment to deliver something of value, but not made a commitment to the planning for the whole project.

One of the key benefits of using #NoEstimates as a planning approach is that we create more Options, making our projects more valuable and more flexible.

In the #NoEstimates approach we release a partial set of functionality (value) earlier. We may find that for the time being that functionality is enough and may decide not to release any further functionality (an option). Or we may find something we did not know before, and change the project (another option). While in the Estimated approach we will make commitments in terms of time, people and resource allocation that are going to be harder to change later (reducing options), and may commit more money to the problem than we actually need (less options still).

With the #NoEstimates approach we don't commit to requirements that we are not going to immediately work on

Note also that with the #NoEstimates approach we don't commit to requirements that we are not going to immediately work on. The reason is simple: requirements have a "best before" date and expire. We should not commit to requirements too far into the future - but that we will tackle in another post.

Have you applied this planning heuristic in your projects? What were the benefits, and obstacles you faced when using it?

Photo credit: psiaki @ flickr

Labels: , , , , ,

at 07:00 | 3 comments